Engineering case

Engineering case

Cross Sea Steel Platform Project


Overview: Located in a logistics park in Daxing District, Beijing
Project scale: including three-story steel platform, three-story attic, and laminate shelves, steel structure platform 8800 flat attic shelves 1200 flat, laminate shelves part 2000 groups, project amount 800w
Solution: The project duration is tight, and it is still carried out during the National Day. The two warehouses total 5600 square meters of warehouse, the production and installation cycle is only a month. During the installation period, the construction, hoist, fire power distribution, ground and other multiple simultaneous construction cross-operation, installation peak more than 40 workers to install. Jiuwei demonstrated excellent project management and execution capabilities and successfully completed the delivery of the Wanping Steel Platform Loft project in just 40 days.
 